patching...
Breaking: Firefighters Knock Down Second-Alarm Fire »
Welcome back, Patch Blogger!

New Sakonnet River Bridge To Open Today

While the Sakonnet River Bridge's northbound lanes will open to traffic today, the bridge's southbound lanes could also open as early as next week, says the DOT.

 

The new Sakonnet River Bridge is scheduled to open to Route 24 northbound traffic today, Sept. 20, eliminating the 18-ton weight limit for northbound traffic, announced the Rhode Island Department of Transportation (RIDOT) on Wednesday. 

In approximately one week, the new bridge also will carry southbound traffic, according to the DOT. 

“With tomorrow’s milestone opening of the new Sakonnet River Bridge to northbound traffic, we will reduce the lengthy detour that the motoring public has used over the past four years,” said RIDOT Director Michael P. Lewis. “We thank the two host communities of Tiverton and Portsmouth for their continued patience and support during this project.”

The new bridge is 2,265 feet long and approximately 96 feet wide. There are two 12-foot lanes in each direction with wide shoulders. Mariners will find a wider passage under the bridge’s center span and the new bridge maintains the minimum vertical clearance over the river of 65 feet. 

Once all traffic has been shifted to the new bridge, work will continue on approach roads on both sides of the span. Demolition of segments of the old bridge must take place before this work is finalized. RIDOT expects construction activities on the segments of Route 24 approaching the bridge to be ongoing through spring 2013.

All construction on the new bridge is expected to wrap up in 2013, including the opening of a bike path along the northern edge of the new bridge and the connecting paths to local streets on both sides of the bridge. Work on the bike path approach segments is expected to begin in Spring 2013.

The new Sakonnet River Bridge was slated to open in May, but structure safety concerns pushed back the deadline.

The project’s contractors, the Cardi Corp., are required by contract to pay the state $26,500 per day they go over the completion deadline. The bridge was expected to open on May 11. 

Also in 2013, RIDOT expects to advertise for a construction project for the demolition of the old Sakonnet River Bridge.

Related Topics: Bridge Tolls and Sakonnet River Bridge

Tracey H

11:30 am on Wednesday, September 19, 2012

Do you know what time it will open?

Reply
Comment_arrow

Jim L

2:51 pm on Wednesday, September 19, 2012

if it opens tomorrow then they will shift all the blocks tonite, there will be big yellow barrels with baskets for toll practice, change only, we don't want our dollars just blowing away

Robert E

11:55 am on Wednesday, September 19, 2012

They need to hurry up and open it before it fall down.

Reply

Jim L

2:54 pm on Wednesday, September 19, 2012

you have to do the circuit, drive the new Sakonett bridge and then the escape bridge, but hurry because the toll booths will, be blocking the view
soon

Reply
Comment_arrow

Mark D

7:00 pm on Wednesday, September 19, 2012

What toll booths, there will be no toll booths.

John ("Anything But Sue")

7:55 pm on Wednesday, September 19, 2012

Who wants to be the FIRST ... I have it from a Reliable source in Bristol that privately,..bridge officials are recommending that until the safety of the new bridge is established, ...all people crossing the new bridge should have PFDs for each person in the vehicle. (PFD= Personal Floatation Device). Just sayin'.

Reply

John ("Anything But Sue")

8:01 pm on Wednesday, September 19, 2012

I have just been authorized by my source in Bristol to release that sources name. Bill Carson. YUP

Reply
Comment_arrow

OldTownie

8:35 pm on Wednesday, September 19, 2012

Hahahahaha, thanks that was great!.

Leave a comment